Voith to modernise Albbruck-Dogern equipment

11 April 2013


Voith is to modernize several turbines and supply three vertical Kaplan runners for the Rheinkraftwerk Albbruck-Dogern hydropower project on the German-Swiss border in a €25M contract.

Project owner Rheinkraftwerk Albbruck-Dogern AG (RADAG) awarded Voith a multi-phase contract for the modernization work. The first contract stage covers the modernization of one machine set with an order volume of €10M, while the remaining two machine sets will be refurbished in the next project phase. In total, the order is worth approximately €25M.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.