|
||
| |
|
Bringing together Chinese and foreign contractors on the world’s largest construction site is a complex and demanding task. Adrian Greeman went to see how work at the Three Gorges site is organised For Shiu Fung Yu, one of China’s many female construction workers, it is an honour to be working on the Three Gorges dam project on the Yangtze river. ‘It is very famous’ she says, besides ‘being in a nice environment’. And of course she needs to have a job.She came there from Sichuan province a month ago, one of thousands of new workers moving onto site as the main concreting and construction begins for the dam itself. She will stay, along with her husband who also works there, for the next five years. A peak workforce of 25,000 is expected, 18,000 of whom are already there. Behind her, as she walks off the afternoon shift, can be seen a small forest of cranes, conveyors, drills and excavators. They rise from the depths of 85m deep excavations between two giant cofferdams. Completion of these cofferdams last year finally sealed off the main construction area from the Yangtze, the world’s third biggest river and one of its most tumultuous. With completion of phase one of the project, the five-year river diversion was over, and dam construction began. The sheer cliff of the left bank is where the nearly vertical penstock channels are being concreted for the first of the 14 turbines. At the top, stand the silhouetted shapes of the first steel liner sections. Below, the box-like forms of the powerhouses are nearly complete and ready for installation of mechanical equipment. Western firms have contracts for all fourteen 710MW turbines and generators. Eight of the contracts are with a European group of Alstom from France and Switzerland’s ABB, six more are with a transatlantic alliance of GE of Canada, and Germany’s Voith and Siemens. On the far side, mid-river, is the vertical concrete wall of the lateral coffer dam behind which runs the river in the diversion channel. On top is the steel lattice pylon of German firm Krupp’s ‘Blondin’ or cableway crane system which, despite its capacities, will not be used primarily for concreting but for lifting formwork, machinery and other equipment into place. The task of placing more than 16M m3 of concrete, enough to build a half dozen of the world’s big dams, will be handled by combined tower crane and conveyor systems, four from Rotec of the US and two from a specially developed system from France’s Potain and Japan’s Mitsubishi. A host of Chinese goose-necked cranes will assist, along with delivery trucks and much else. Closing the river All this is gearing up to begin. Meanwhile, the achievements of the huge project are already enormous. Phase one, beginning in 1993, saw the transformation of the river close to the town of Sandouping from a slow stately bend around a steep headland into a huge diversion channel and the now dry site. A small island midstream, Zhongbaodao, was lengthened and elongated into a vast longitudinal concrete wall in the middle, while the channel beyond was sealed off, widened to 300m and deepened by removal of some 10M m3 of river bed to accommodate the maximum 50,000m3/sec flood season river flow. Meanwhile through the headland two canyons were blasted, the larger involving an excavation of more than 40M m3 of the solid 1000N/mm2 granite of the area. Work also included a complex series of tunnels and adits for the lock water feed and discharge system. Concrete construction is now underway for the twin channels for the two-way five-step shiplock that will allow up to 3000dwt vessels to bypass the completed dam. A huge improvement in river navigability is one of the spin-offs of the dam work. The contractor is the Armed Policeman and the 378 Joint Venture. A smaller channel closer to the dam itself was also created in which a shiplift is now being installed. This channel now serves as the through route for the river traffic during the flood season in July to September, when the main diversion channel is too dangerous for boats. Phase one work also included some of the concreting for the side wings of the dam, the construction of a 1000m span suspension bridge, the Xiling, which is China’s longest at present, and a motorway covering 26km of the 40km to Yichang city downstream. Ten major domestic contractors were involved, mobilising 20,000 workers, and nine design institutes from around China supervised the construction. The conclusion to phase one came in November 1997 when thousands of pyramid shaped concrete blocks, and granite boulders from the ship lock channel, were tipped into the river to seal the site, witnessed by then premier Li Peng. ‘Closure of the river was completed successfully on 8 November,’ says Li Jun Lin, senior engineer with the Three Gorges Project Development Corporation (TGPDC), the autonomous body set up as client and operator for the project which also runs the design work. The initial cofferdam was a 69m high rock and earthfill embankment behind which was built a second 73m high embankment. The area between the two was infilled, mainly with sand and finer material, and a waterproof diaphragm wall was added using equipment supplied by Germany’s Bauer. Smaller embankments formed a higher top to the wall and in summer 1998 an additional dike was added during the freakishly high river flows that caused the terrible devastation downstream. In the event, says Li, the extra 5m was not needed as the peak river level only reached around 75m. The work at the 15km2 dam site was barely affected by the dramatic events which saw such heroism on the levees, and the cofferdam was completed on time in August. Meanwhile, between the 26M m3 of the upstream temporary dam and its smaller downstream sister, de-watering was able to begin in June last year, and the dry area for excavation was ready in September. Pumping was not easy in such a deep pit, says Li. At the bottom the ground was prepared with removal of river bed material to bedrock. ‘There was a 6m to 8m thick layer of silt, mostly deposition caused by the Gezhouba dam downstream,’ says Li. This smaller hydroelectric dam was completed in the late 1980s, close to Yichang. ‘Below that was harder earth and stones and needed blasting, although blasting of the last metre is forbidden because of the danger of causing rock damage,’ says Li and so a water jet technique was used to loosen spoil. Some 18.2M m3 of excavation was required for the river bed and powerhouse areas. Base rock quality was as good ‘as we expected’ says Li, pointing out that site investigations had gone on for more than 20 years and ‘we knew what to expect’. The base rock is a granite with limited cracking and reasonably cemented. On this area the main concreting operation has been under way since January. Beginning phase two Phase two of the dam comprises the major central section of the dam, the 483m long spillway section, and the powerhouse section, with its 14 turbines, stretching 643.7m on the left bank. Another 584m long section with 12 turbines will be built later in the current diversion channel. Side sections bring the total dam length to 2309.5m. All this will eventually be a 185m high concrete bastion, a sloping mass of concrete that will total over 16M m3. Some two-thirds of that will be poured in the current phase with peak annual placings of 4.5M m3 and monthly throughputs of up to 550,000m3. It is a lot of concrete, and will require unparalleled organisation. The TGPDC has brought in a large amount of western equipment for the operation, much of it selected, purchased and then maintained by a special equipment division (see panel). Plant and machinery is allocated to the major contractors — five groups of companies who have won contracts on phase two works. They are all domestic firms, selected by public bidding in the internal Chinese market, which is becoming normal practice in the country. For the major concreting works, the choice was between crane–skip placement with tower cranes, and/or a cable way crane, or conveyors. The latter system has been used effectively on several previous dams like the Ertan in Sichuan, and the Xiaolangdi Yellow river dam, though with much smaller quantities. A big Rotec conveyor system was also used for the longitudinal cofferdam in phase one. Here, finally, the choice has been to use conveyors, mostly a Rotec system from the US, large tower suspended units that swing across the dam blocks as required. But there are also two spectacular giant Potain cranes fitted with conveyors, made by Mitsubishi, which serve the same function. The 150m high lattice boom towers for a Blondin cableway crane are also being installed by Germany’s Krupp Fordertechnik. Two units are on site, says Martin Michelitsch, the installation supervisor. Each has a 25t capacity which means theoretically a 6m3 skip for concrete can be carried. At times they will be used for awkward corners and the highest points on the walls but mainly they will be used for carrying plant, equipment and formwork. Concrete will be delivered by fixed conveyors also being supplied by Rotec, though a fleet of Terex concrete skip trucks is also being used. These will help feed concrete from four major batching plants including one from Italy’s Cifa, an American C S Johnson plant and others. Possibly the world’s biggest aggregate crushing plant has also been assembled. Construction of the powerhouse is being carried out under a separate contract by Gezhouba Group and the Qingyun Joint Venture. In fact concreting for the first six powerhouses has been completed because 378 Joint Venture was able to begin early, carrying out excavation during phase one in 1996 and concreting in January 1997. Excavation for the other seven powerhouses is now almost finished and concreting started. All of this has meant the turbine suppliers have been able to work on site for a few months now, and the shapes of the intakes and tailraces are already becoming apparent. The task of building 710MW units is unique, and in the words of the Three Gorges Corporation ‘very arduous’. Contracts The two sets of contracts were let in 1997, Alstom/ABB’s for US$400M and GE Canada/Siemens for US$300M. Alstom’s component is worth US$212M to design and install eight of these giants, which will utilise an 80.6m fall, the water rotating a 10.6m diameter turbine at 75rpm. Each unit is 5.5m high and weighs 440t. Main components will not be delivered until between January 2002 and August 2004 but the team is settling in well at site. Initial works have begun well, according the Mathieau Didier, Alstom’s main representative at the dam, who will co-ordinate supervision and commissioning.
|
Buyer's Guide
Site Search
Site and archive search |
|||||||||||||||||||||||||||||||||
|
International Water Power and Dam Construction ©2010 Published by Global Trade Media, a trading division of Progressive Media Group Ltd. Terms & Conditions |
|
|
|
|
|
|
|
|