The Lesotho Highlands Development Authority (LHDA) has awarded two geotechnical investigation contracts for the proposed 120MW Oxbow Hydropower Scheme in Lesotho, advancing preliminary engineering for the project.

Oxbow is the preferred hydropower scheme under Phase II of the Lesotho Highlands Water Project (LHWP). The fully underground facility is planned to operate as a peaking plant for six hours a day, seven days a week, improving electricity supply security and reducing Lesotho’s dependence on imports. It will supplement the country’s existing 72MW ‘Muela hydropower station, developed during Phase I of the LHWP.

The investigations are divided into two phases. Open Ground Resources has been awarded the first contract, valued at R6 million, covering geophysical investigations, field mapping and related surveys. The work is expected to take approximately five months.

The second contract, worth approximately R100 million, was awarded to South Africa’s GEOMECH AFRICA in early August. It covers borehole drilling, in-situ testing and laboratory analysis, with completion expected in approximately 11 months, including nine months of field activities. Subcontractors include South African companies Skyhorse Aviation and Open Ground Resources, and Germany’s Sol Experts.

The drilling programme comprises 18 vertical, inclined and sub-horizontal boreholes with a combined length of approximately 2648m. In-situ investigations will include hydraulic conductivity testing, groundwater piezometric level determination, Lugeon testing, hydraulic fracture stress logging and standard penetration tests.

Laboratory analysis will assess properties including acid-soluble chloride and sulphate content, potential alkali–aggregate reactivity and water absorption, alongside methylene blue testing, X-ray diffraction and petrographic analysis.

The investigations will help characterise subsurface conditions and mitigate geotechnical risks that could arise during construction.

Engineering work on Oxbow began in early 2025 following the appointment of ASG Joint Venture as the engineering design and construction supervision consultant in late 2024. The joint venture comprises Artelia of France, SMEC International of Australia, SMEC South Africa and Lesotho’s GWC Consulting Engineers.

Environmental and social impact assessment work began on 6 January 2025 and is expected to be completed in 2027. The assessment is being undertaken by ELC-Consultant Joint Venture, comprising Italy’s ELC, Lesotho’s Greenway Consultancy and South Africa’s Green Gold Group.