Preparatory work is underway at the 30MW Gravfoss II run-of-river hydropower plant in Modum municipality, Norway, ahead of a scheduled outage in February that will initiate the replacement of major electromechanical components. The overhaul, led by utility Å Energi Vannkraft, has a revised budget of NOK 250m ($22.6m) and is engineered to secure reliable renewable generation for at least another 30 years without altering the plant’s installed capacity.
Commissioned in 1996 at the outlet of Lake Tyrifjorden in Buskerud county, the plant operates a single Kaplan unit with an average annual output of 219 GWh. Because the facility is run-of-river with no upstream regulation reservoir, water cannot be impounded during maintenance outages, placing a premium on strict timeline management to minimize spill and foregone generation.
“We are currently in an important preparation phase. Our aim is to complete as much work as possible before generation stops in February and the replacement of the main components begins. This will be the most demanding and critical phase of the project,” said Ruben Moritz, project manager at Å Energi Vannkraft.
To de-risk the forthcoming outage, contractors have already completed cabling between the dam, powerhouse, and emergency power generator. On-site teams are currently assembling the new stator inside the machine hall, while installation work on the station ventilation system and fire dampers nears completion.

Original cost estimates for the modernisation were pegged at NOK 200m, but the budget was raised to NOK 250m after technical evaluations early in the execution phase identified the need to broaden the project scope.
The electromechanical package has been split between GE Vernova, who is supplying the new generator stator and executing the full rehabilitation of the generator unit, and Andritz Hydro, who is delivering the instrumentation and control system, a new oil-free runner, and conducting extensive rehabilitation of the Kaplan turbine, turbine hatch, and cross-swing gate.
Regional contractors, including Multiluft and Krøderen Elektro, are delivering balance-of-plant, electrical, and HVAC packages.
“Strong cooperation between our suppliers, the operations team at Å Energi Vannkraft and the project team is essential to delivering the upgrade safely and efficiently. Working together, we can ensure thorough planning and effective solutions throughout the project,” Moritz noted.
The modernisation forms part of the Å Energi Group’s long-term NOK 35bn capital program directed toward grid infrastructure and hydropower asset management across Norway. Complete recommissioning of the Gravfoss II facility is scheduled for late 2027.