Rehabilitation works carried out above water for headrace channel, St Pantaleon, Austria
The 3,700 m headrace channel at St Pantaleon is operated by Ennskraftwerke, Steyr for power production for one of its hydro-electric power plants. The channel, located 25 km south of...
Construction of two dams with asphaltic concrete cores in Norway
Dense Asphaltic Concrete is used globally to line upstream dam faces, reservoirs, channels and landfill. For over 50 years it has also been successfully used as a specialist method...
Upgrade of upper reservoir increases power production efficiency at Goldisthal, Germany
Goldisthal pump storage scheme is situated 50 km south of Erfurt in the Thuringian Mountains, Germany. The power station, operated by Vattenfall Hydropower Generation, has a power...
Rehabilitation of lining of 11.3 km long sections of headrace channel, Alz channel, Bavaria
The Alz channel is a manmade 18 km long headrace channel, which provides water for power production and cooling purposes for Wacker Chemie AG, a chemical factory employing 10,000...
REHABILITATION OF KINZIG DAM, GERMANY
The Kinzig Dam (built in 1976 -1981) is located in the Main-Kinzig area, east of Frankfurt, Germany. The dam is part of a flood protection scheme and also functions as a small HEP...
REHABILITATION OF ULMBACH DAM, GERMANY
The Ulmbach Dam (built in 1964/5) is located in the Lahn-Dill area, north of Frankfurt, Germany. It provides flood protection and is also a tourist destination, attracting...
MASTIC RENEWAL OF UPPER RESERVOIR AT LA MUELA, SPAIN
The Pump Storage Scheme at La Muela in Valencia is the biggest of its kind in Spain. The upper reservoir has a circumference of 4,800m and stores 23 million m3 of water, generating...