Siga-Hydro has opened the final phase of pre-application public consultation for the Silvermines Hydro pumped storage project in County Tipperary, Ireland.
The six-week Stage 3 detailed design consultation runs from 9 November to 21 December 2026. Feedback will be reviewed before the design is finalised and a planning application is submitted.
The project would repurpose a former mine site, using the existing mine pit as its lower reservoir and constructing an upper reservoir higher on the mountain.
According to its latest newsletter, Siga-Hydro has prepared updated exhibition materials addressing issues raised during earlier consultation events. These cover the site layout, design development and grid connection, alongside water management, drainage, wetlands, biodiversity, landscape and environmental protection.
The materials also address construction activities, traffic management, road safety, noise and measures to minimise disruption. Information on public amenities, employment opportunities, socio-economic benefits and a Community Benefit Fund will also be presented.
A public exhibition will take place at Hickey’s Lounge in Silvermines Village on 3 December, from 3pm to 8pm, and 4 December, from 2pm to 7pm. Members of the project design team will attend to discuss the proposals and receive feedback. This will be the project’s fourth public event and its last planned exhibition before the planning application is submitted.
Consultation materials will be available on the project website throughout the consultation period. Exhibition boards will also be displayed at Nenagh Library from 7 to 21 December.
Silvermines is progressing through the permit-granting procedures for European Projects of Common Interest. Development work includes geological surveys, habitat checks, water studies, environmental reviews and engineering design.
Written submissions on the design proposals must be received by 5pm on 21 December. Comments can be submitted to community@silvermineshydro.ie or in writing to Siga-Hydro’s Nenagh office, with comment forms also available at the exhibition and library display.
The consultation follows 18 months of community engagement. Once the planning application is submitted, members of the public will have a further opportunity to make formal submissions or observations through the statutory planning process.