Alstom wins refurbishment contract at Norwegian hydro plant

5 September 2014


Norway's Energiselskapet Buskerud (EB) has awarded Alstom a €4 million contract to repair and refurbish the existing generator at the 25MW Døvikfoss hydro power plant.

Dismantling works started at the project in May 2014 in order to limit the loss of energy at the project, with the assembly of the new and refurbished parts expected to be completed in June 2015.

“The hydropower plant is important for our energy supply in this region and we have chosen Alstom because of their competitive offer and their experience and expertise from similar types of projects", said Erik Andersen, Executive Vice President Production of EB.

“Our hydropower experiences and our dedicated services team will be fully commited to refurbish the Døvikfoss hydropower plant in the most optimal way. This contract shows our commitment to the Norwegian hydro market", added Eric Staurset, Country President of Alstom in Norway.

Located in the community of Modum, in south eastern Norway, the Døvikfoss hydropower plant was built in 1975 and exploits a head into the 48km long river named Drammenselva.

Alstom has successfully completed other hydro projects for EB in Norway, including the Mykstufoss and Kaggefoss rehabilitation projects.

Image: Dovikfoss hydro power plant, Norway ©EB



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.