Andritz to rehabilitate equipment at Old Hickory hydropower plant, US

1 March 2023


Andritz has been contracted by the US Army Corps of Engineers’ Nashville District to rehabilitate the turbines and generators at the 162MW Old Hickory hydroelectric power plant on the Cumberland River in Central Tennessee, US.

Scope of supply includes the design, manufacture, transport, erection, testing and commissioning of three Kaplan turbine generator units with a capacity of 40.5 MW each, along with associated auxiliaries and ancillary equipment, with an optional fourth unit. The contract will be executed by Andritz’s US subsidiary in Charlotte, North Carolina.

Once fully commissioned, power generation is estimated to be about 565 GWh per year. Commissioning of the first unit is expected in August 2026.

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.