Bauer provides further foundation engineering work for Bhutan hydro plant

5 March 2020


Bauer Spezialtiefbau GmbH has been contracted by Jaiprakash Associates Limited to carry out specialist foundation engineering work for the Punatsangchhu-2 hydropower project in Bhutan following the collapse of an underground cavern at the project.

Bauer’s engagement on the project follows earlier work in 2014-15 where it executed injection work to seal the project’s upstream cofferdam. 

The new contract instructs Bauer to carry out 18,000m of soil injection for subsoil stabilization as well as install 19,000m of tie-back anchors. Along with various equipment for the injection work, up to five drilling rigs are being used at the same time, including KR 806 and KR 909 rigs from KLEMM Bohrtechnik GmbH. 

Bauer's work on Punatsangchhu-2 will take around 15 months.

 

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.