Breakdown of the scheme’s overall costs

1 January 2000


Breakdown of the scheme’s overall costs
Item Cost % of total
Consultancy costs    
(Includes: feasibility study, topographic and river surveys, ground investigations, consultations, environmental assessment, reporting, design, etc) £599,000 (US$943,063) 10.8%
     
Environmental agency costs £414,000 7.5%
(Includes: client costs, environmental inputs, ECC Project Manager, landowner compensation) (US$651,792)  
   
     
Site supervision    
(Includes: ECC Supervisor and staff) £329,000 (US$517,970) 5.9%
     
     
Construction    
(Includes: out-turn, including £4.2M (US$6.6M) 75.8%
compensation events) £5.5M (US$8.7M) 100.0%



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.