Bulgarian project to be upgraded

3 May 2006


The project involves the refurbishment of the three power plants of the Dolna Arda hydro scheme, which consists of Kardjali power plant (four machine sets with a total output of 106MW); Studen Kladenez power plant (four machine sets with a total output of 60MW); and Ivailovgrad power plant, which has three machine sets totalling 103.5MW.

In addition, Studen Kladenez’s capacity will be increased by an additional 16MW. The construction work for this part of the project will be carried out by PORR Technobau und Umwlet as a separate contract worth approximately US$22.2M.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.