EL Cajon contract awarded

1 April 2003


MEXICAN CONSTRUCTION company Empresas ICA Sociedad has announced that the Federal Electricity Commission (CFE) has awarded the El Cajon hydroelectric project to Constructora Internacional de Infraestructura.

This consortium includes two ICA subsidiaries, Promotora e Inversora Adisa as the project leader with a 40% shareholding, and Ingenieros Civiles Asociados, with 25%. energomachexport Power Machines and Peninsular Compania de Constructora own 20% and 15% of the consortium, respectively.

The bid presented by Constructora Internacional de Infraestructura was for approximately US$750M, with a term of completion of 1620 days.

The El Cajon project, in the state of Nayarit, comprises the execution of civil construction, electromechanical and ancillary work including procurement, engineering, fabrication, transport, assembly, testing, start-up and commissioning of two turbo-generating units with a guaranteed combined design power rating, under different hydraulic loads, in excess of 670MW.

This is the first EPC contract for the complete execution of a hydroelectric project, under the financed public works programme. Under this programme, the contractor obtains financing for the whole amount, and the client will pay upon completion.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.