Equipment contract awarded for Albbruck-Dogern

1 May 2007


Construction of the 24MW generation set involves supply and installation of a 6.1m diameter bulb turbine and generator. The entire housing of the set will be submerged in the river at the weir power station, and take the total installed capacity at the site to 100MW.

The new plant is to be commissioned and brought online in 2009. Work on the site has also included rehabilitation of the weir and will require installation of a fish passage.

The Albbruck-Dogern is three quarters owned by power utility RWE. The E&M contractor is a subsidiary of Austria-based Andritz VA Tech Hydro.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.