FERC clears Ameren to start Taum Sauk rebuild

16 August 2007


Key conditions set by FERC for the rebuild include submission of designs for approval as well as a plan and schedule for impounding the new reservoir. In addition, the conditions include a reforestation plan, reduced effects on wetlands, and re-opening limited recreational facilities at the lower reservoir.

In February, Ameren submitted plans and an environmental report to FERC. The utility envisioned the upper reservoir being impounded behind a new roller compacted concrete (RCC) dam.

FERC added that it also required to meet with all parties concerned with the scheme - Ameren, the design consultant, the Board of Consultants, and the contractor - upon award of the construction contract.

In a letter to Ameren, FERC said it wanted to make all parties aware of its 'authority in the construction process'. It added: 'Given the critical nature of this construction with regard to dam safety and public safety, establishing clear lines of communications prior to construction is essential.'

The final environmental assessment (EA) for the project was issued 14 August following feedback from the public consultation on the draft EA, issued early June.


Related Articles
AmerenUE plans to rebuild Taum Sauk
Taum Sauk reservoir breached
State to investigate dam failure
Consultant delivers Taum Sauk verdict
AmerenUE in largest ever FERC settlement
Ameren management blamed over Taum Sauk failure



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.