First units commissioned at Jebel Aulia

4 March 2004


The first ten Hydromatrix turbines were put into commercial operation and have been supplying electricity since early January 2004.



VA Tech Hydro was awarded the Jebel Aulia contract by Sudanese power supply company, National Electricity Corporation in 2001 The entire scheme comprises 80 units including the required mechanical and electrical auxiliary systems as well as a new dam crane.

The 80 turbine-generator sets at the 30.4MW Jebel Aulia power plant will be installed in 40 modules. Installation work on the next units has already begun, with 10 turbine units expected to be commissioned every two months.

Full operation of the power plant, located on the White Nile about 40km south of Khartoum, is scheduled for early 2005.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.