Funds approved for Estonia’s first pumped storage project

31 October 2022


Eesti Energia has received €584,950 in funding for development of Estonia’s first pumped storage project.

The joint agency of EAS and KredEx approved the funds to help prepare construction of the 255MW facility at the Ida-Virumaa mine site. Plans for the project are moving at a good pace, Eesti Energia said, with the preliminary environmental assessment of the site expected to be complete in early 2023. 

According to plans, the project’s upper reservoir will be built on a tailings structure, and a closed mine will be used as the lower reservoir. The project is expected to start operating in 2026.

 

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.