Construction of many hydropower projects started by Nepal Electricity Authority has been affected by the earthquake which shook the country in April, according to reports in the Kathmandu Post. The situation is being complicated further by fuel shortages following an Indian blockade which is contributing to projects not being completed on time.

Authorities say that Chameliya Hydropower, Upper Trisuli A, Kulekhani III and Rahughat projects have been hit hard.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.