LHWP Phase II hydropower component underway

26 October 2022


The Lesotho Highlands Development Authority (LHDA) has marked another significant milestone in the implementation of Phase II of the Lesotho Highlands Water Project (LHWP) with the start of procurement for the design and construction supervision of the Oxbow Hydropower Scheme.  

This follows the completion of further feasibility studies into the hydropower component of Phase II, which recommended conventional hydropower as the more feasible option to meet Lesotho’s energy needs. Three potential sites were identified:  two on the Senqu River and the third at Oxbow on the Malibamats’o River. In November 2021, the government of Lesotho confirmed the Oxbow Hydropower Scheme and gave the go-ahead for the hydropower engineering, Environmental and Social Impact Assessment (ESIA) and the Resettlement Action Planning (RAP) studies.   

The scope of the hydropower engineering includes a 100m high dam, two tunnels, high pressure steel penstock (pipeline), 80MW power station, 132kV transmission line, all associated infrastructure such as roads and accommodation, bulk power and telecommunications infrastructure and enviro-social components. 

 Broadly, the enviro-social components will include studies on public health, cultural heritage, terrestrial ecology and water quality elements, resettlement and livelihoods restoration elements to mitigate the impact of the Oxbow Scheme on the environment and communities in the project area.  

“The Oxbow Hydropower Scheme is the third major engineering component of Phase II,” explained LHDA’s Chief Executive, Tente Tente. “LHDA is confident that it will attract the interest of local, regional and international consultancies with the experience and expertise to deliver engineering projects of this nature. Given its scope, it will be a significant boost to the engineering and construction sector and the economy of the region.”

“The Oxbow Hydropower Scheme increases security of power for Lesotho and will reduce the country’s dependence on electricity imports. The power generated at Oxbow adds to the additional 40% of electricity that will be generated at ‘Muela as a result of the increased flow of water from Polihali,” added Ntsoli Maiketso, LHDA’s Divisional Manager, Phase II. 

Water transfer to South Africa will commence in 2028 with the completion of the Polihali Dam and Polihali Transfer Tunnel and the Oxbow Hydropower Scheme will be commissioned in 2029, one year later. 

 Interested firms have up to 13 March 2023 to submit their bids. Specific information on the procurement is available at https://www.lhda.org.ls/tenderbulletin/currentProcurement.aspx

“The procurement for the associated Environmental and Social Impact Assessment (ESIA) and Resettlement Action Planning (RAP) is taking place concurrently,” added Tente. “Interested bidders are advised to check the Phase II Tender Bulletin on the LHDA’s website for the Specific Procurement Notices which will be published shortly.”  

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.