Modernisation planned at Reckingen

9 June 2003


The scope of supply for va-tech-hydro includes a set of new runner blades, a guide wheel ring, a discharge ring, and draft tube cone to allow for an increase of the runner diameter from 6200mm to 6450mm. The remaining mechanical components will be overhauled thoroughly. Furthermore, the existing turbine controller will be replaced by a digital TC 1703 governor of the Neptun series.

This upgrading project is designed to boost the annual energy production of the refurbished turbine No 1 by 3%. A subsequent upgrading of turbine No 2 would result in a 5.7% increase in overall energy output. Once one turbine is modernised, the additional annual energy production of more the 7500MWh will supply approximately 2500 households.

Reconstruction and modernisation work is scheduled to start in January 2004. The total downtime from shutdown to recommencement of commercial operation has been planned to be only 21 weeks.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.