New hydro power capacity requirements as identified by the Vision Paper

1 January 2000


New hydro power capacity requirements as identified by the Vision Paper
Plan Period Likely hydro Likely funds
  capacity addition requirement
  (MW) (US$)
9th Plan (1997-2002) 5800 4.7B
10th Plan (2002-2007) 10,432 8.5B
11th Plan (2007-2012) 21,288 17.4B
12th Plan (2012-2017) 23,000 18.8B
13th Plan (2017-2022) 31,000 25.3B
Part 14th Plan (2022-2026) 35,000 28.5B
Total 126,520 103.2B
India’s vision aims for 32% hydro power



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.