Norway’s Blaafalli Vik to receive GE turbine

7 October 2004


Under the terms of the deal, GE is to supply a 235MW 365.5m head vertical Francis hydro turbine; a vertical, synchronous generator with excitation system; mechanical balance-of-plant equipment and spare parts as well as carry out design and engineering; transport; training; installation and commissioning.

Deliveries to the new facility, currently under construction some 110km from Bergen, are to begin next January and will continue until November 2005.

When Blaafalli Vik is commissioned in September 2006, it will take over from the existing Blaafalli 1 and Blaafalli 2 power stations, which are scheduled for decommissioning.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.