Plutonic signs contract for Toba/Montrose construction

24 September 2007


The engineer, procurement and construction (EPC) contract is valued at Can$500M (US$499.8M). While access road and bridge construction started in July, the new contract enables further works to proceed for completion of the project with the two power plants - the 123MW East Toba and 73MW Montrose Creek.

In a statement, Donald McInnes, president of Plutonic, said: 'Execution of the EPC contract is a significant milestone for the Toba Montrose General Partnership as it provides price, date and performance certainty for our lenders, stakeholders and members of the community.'

He added: 'Kiewit has an exceptional reputation in building utility-scale run-of-river projects in environmentally sensitive areas.'

Separately, Kiewit has agreed a contract with va-tech Hydro to build 14 turbine-generators and supply intakes and governors for two power plant groups in British Columbia.

Plutonic has a portfolio of 34 hydro projects in various stages of development with a total design capacity of 1.7GW to generate approximately 5500GWh per year. The Toba/Montrose scheme is the most advanced.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.