Repair work starts at Toddbrook reservoir, UK

7 January 2020


Work has started on a project to repair and enhance the resilience of the Toddbrook dam wall and spillway in Derbyshire, UK, following damage sustained during heavy rainfall in August 2019.

The Canal & River Trust announced that temporary works started on Monday 6 January on the auxiliary spillway. A protective, waterproof nib will be inserted all along the spillway crest which will reach down into the clay core. The spillway crest will be increased in height by just over 1m at either end and concrete waterproof barriers will be installed on the spillway slope to channel any overflowing water into the central undamaged section which will be lined for extra protection.

The new features will ensure that the dam is secure in any extreme weather events. They will remain in place until permanent reconstruction of the dam is undertaken.

The current works to the dam will be followed later in 2020 by improvements to the Todd Brook inlet channel at the head of the reservoir. This will provide greater control over how much water flows from the brook into the reservoir or around the reservoir via a bypass channel. This project will also include the installation of a new footbridge across the brook.

The Canal & River Trust, which cares for Toddbrook Reservoir and 2000 miles of waterways across England & Wales, is working closely with contractors Kier to keep the reservoir drained as preparations are made for its long-term repair a process that is likely to take several years and cost around £10 million.

After the emergency in August, the masonry weir at the inlet channel at the dam project was raised with the installation of mesh baskets filled with sandbags. In the year ahead, these will be replaced by a footbridge incorporating sluice gates, to provide a higher degree of control over water flows.

The Trust will continue to monitor the bypass channel closely, with expert hydrologists having carried out extensive modelling to assess the topography and the maximum capacity at all points along its course. During normal weather conditions, while the reservoir remains drained, all flow is sent down the bypass channel.

Long term plan and inquiry update

The Trust has commissioned an independent inquiry into what caused the damage to the auxiliary spillway. It is also assisting with an independent review commissioned by the government. Both these reports are due to be published early in 2020 and will guide the long-term repair of the dam.

Simon Bamford, asset improvement director for the Canal & River Trust, said: “We are keen to hear the findings of the independent inquiries so we can move forward and decide how best to fix the dam for the long term. Once we know what caused the damage to the dam we will be able to work out a detailed plan for repairing it, including a precise timetable and costings. In the meantime, we will be doing some work to protect the reservoir and further improve its resilience against any extreme weather events.

“We know a footbridge has been on the wish list of some local residents, so we are delighted we can incorporate this into the design for improving the inlet.”

Temporary repairs to the spillway started on 2 August 2019

An RAF Chinook helicopter was used to drop tonnes of aggregate to fill an erosion hole that had formed following the flood event



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.