Small hydro plan for Austrian weir

23 April 2004


The scheme is to be built near Schemerl weir and will consist of a 30m long, 12m wide and 7m high over-flow hollow body weir with attached pneumatically operated spillway gates. It will also feature twelve VA Tech Hydro Hydromatrix units and an operation building.

Work is to be carried out by VA Tech Hydro in consortium with its Austrian-based partners Porr Technobau and Verbundplan, the leader of the group, with commissioning of the plant expected in summer 2005.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.