The deal is for the supply of a new vertical 24.7MW Francis turbine to replace two units, rated at 7.5MW each, which are currently installed at the Hauterive hydro power station in the south of Switzerland. The new unit is to operate at a nominal head of 94m.

Commissioning of the upgraded power station, owned and operated by Entreprises Elecriques Fribourgeoises, is scheduled for spring 2006.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.