Located on the Rhine River between Switzerland and Germany, the plant was the first large hydroelectric power plant in Europe when commissioned in 1898.

voith-siemens Hydro will supply four 25MW Kaplan bulb turbines and a separate turbine for minimum flow purposes at the project. With the new units, the plant's average annual production will be raised from 185GWh to 600GWh

Commercial operation for the EUR380M project is scheduled for 2010.

The turbine model was developed jointly by Voith Siemens Hydro and its Japanese subsidiary, Voith Fuji Hydro.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.