Third unit of Indira Sagar synchronised

13 April 2004


NHDC synchronised the first two units on 1 and 12 January 2004, with approximately 180MW being generated from these units. Unit four's stator and rotor have been lowered into the pit and are being made ready for commissioning this month. There are eight units of 125MW each at ISP, with total generating capacity of 1000MW. NHDC has scheduled to commission all of these by December 2004.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.