VA Tech to extend Austrian plant

16 February 2005


The order has been placed by Verbund Austrian Hydro Power AG for VA Tech to supply a six-jet vertical shaft Pelton turbine, including a turbine governor, a sperival valve and a generator, increasing the overall output of the storage plant from 65MW to 200MW.

Under the contract, VA Tech will also be responsible for the installation and commissioning of the new unit. The project is scheduled for completion in May 2007.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.