Voith Siemens wins modernisation contract.

16 October 2002


Kiskoere is located on the Tisza river and was originally put in operation in 1974. The plant generates around 90GWh per year and is equipped with four bulb turbines.

Rehabilitation and modernisation works, including all mechanical and electrical components of the units, will start in summer 2003, with one unit being worked on at one-year intervals. Commissioning of the last unit is planned at the end of 2006.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.