Work starts on Monjolinho

6 December 2004


The US$5.8M Monjolinho plant will be located on the Passo Fundo river, near Nonoai. GE Energy will supply two Francis hydro turbines, each rated at approximately 35MW, 61.8 head and 257.14rpm, together with two 13.8kV, 37.5 MVA vertical axis generators.

Enegevix Egenharia SA of Sao Paulo, Brazil is the engineering, procurement and construction contractor for the project.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.