Fourth unit commissioned at Bureya

7 November 2005


Russian electricity utility United Energy System (UES) held an opening ceremony yesterday, where the CEO of UES Anthony Chubais said the company hoped to launch the station’s fifth and sixth units in 2007, bringing its total capacity to 2000MW.

The first three units of the Bureya plant, which is located on the Bureya river at the junction of the Amur Region and the Khabarovsk Terrirory, began operating in 2003 to 2004.


Related Articles
Third unit commissioned at Bureya
Transmission line to supply Primorsky Territory



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.