Third unit commissioned at Bureya

26 November 2004


Unified Energy Systems invested US$267M in the plant in 2004, with overall investment so far amounting to US$1.23B. When completed in 2009, the plant will be equipped with six generating units with a combined generating capacity of 2000MW.

The Bureya plant will supply electricity to Russia Far Eastern regions and help to prevent floods along the Bureya and Amur rivers. Estimates are that electricity generated by the plant in 2004 made it possible to save the equivalent of 1.75M tons of coal.


Related Articles
Fourth unit commissioned at Bureya



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.