Table 1

1 January 2000


Estimated timeline for implementation of Trung Son hydropower project
Start Finish
Resettlement compensation for road February 2009 December 2010
Access road and bridge construction January 2011 February 2013
Reservoir area compensation December 2010 February 2012
Community Livelihood Implementation Plan activities January 2011 May 2016
River diversion June 2012
Construction of main dam and auxiliaries June 2012 September 2016
Construction of transmission line March 2014 October 2016
Impoundment of reservoir September 2016
First turbine operation November 2016
Full operation May 2017



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.