Table 2

1 January 2000


Table 2: Construction history
July 1993 Kannagawa hydro power field survey office was established
July 1995 The construction of the power plant was approved by the 130th meeting of Electric Power Development Coordination Council
July 1995 The office was reorganised into Kannagawa hydro power plant construction preparation office
February 1997 The office was reorganised into Kannagawa hydro power plant construction office
May 1997 Construction work on the power plant begins
October 2003 Water storage to the lower dam (Ueno) began
September 2004 Water storage to the upper dam (Minamiaiki) began
December 2004 Test run of Unit 1
December 2005 Unit 1 (470MW) started commercial operation



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.